Combined time of a task including all subtasks
Hi Niko,I have a couple of "main tasks" that consist of various subtasks. At the end of the day I'l like to know the time I spent on each "main task" in one figure (as in adding up all the time values of each subtask relating to the "main task"). How do I do that in Timelime? Best, Oliver
Keyboard shortcuts
Generic
? | Show this help |
---|---|
ESC | Blurs the current field |
Comment Form
r | Focus the comment reply box |
---|---|
^ + ↩ | Submit the comment |
You can use Command ⌘
instead of Control ^
on Mac
Support Staff 1 Posted by Niko on 07 Feb, 2020 08:05 AM
Hi Oliver,
What you can do is this:
1. Select your “main tasks” in the task list (left column) of Timelime's main window.
2. Above the calendar (middle column) slide the selector to the left - “Select last day”.
3. Then you can the time spent on these tasks in any of the views in the right part of the main window.
I hope this helps,
Niko