Adding subtask in active task
Hi, actually it is not possible to add subtask to an active project. How can I change this?
Keyboard shortcuts
Generic
? | Show this help |
---|---|
ESC | Blurs the current field |
Comment Form
r | Focus the comment reply box |
---|---|
^ + ↩ | Submit the comment |
You can use Command ⌘
instead of Control ^
on Mac
Support Staff 1 Posted by Niko on 13 Jan, 2022 12:45 PM
Hi there,
There is a rule about nested tasks: Parent tasks can't have timings associated directly with them.
You could add a new “parent task” and make both your existing task and the new task subtasks of it (using drag & drop).
I hope this makes sense to you.
Niko
2 Posted by m23 on 13 Jan, 2022 04:44 PM
Ok, understood. Thanks!